RACI matrix: definition, example and a template to fill in

A RACI matrix, or RACI chart, is a table: one task per row, one role per column, one letter per cell.

  • R, Responsible: does the work.
  • A, Accountable: answers for the result, one per task.
  • C, Consulted: gives an opinion beforehand, the exchange goes both ways.
  • I, Informed: is told afterwards, the information goes one way.
Launching a company website
TaskProject managerDesignerDeveloperClient
Write the briefRCCA
Design the mockupsARCI
Build the pagesACRI
Put the site onlineAIRI

Second row of the table: the designer draws the mockups, the project manager signs them off, the developer gives an opinion beforehand, the client is told afterwards.

RACI matrix, RACI chart, RACI model and responsibility matrix name this same table.

Fill in a RACI matrix

Task

A click on a cell, or the Enter key, moves it from empty to R, A, A/R, C, then I. The R, A, C and I keys set the letter, Backspace empties the cell, the arrow keys move between cells. The matrix takes 30 tasks and 12 roles.

Checks

No issue found.

The matrix stays in your browser and in the link.

Exporting and sharing the matrix

  • Markdown: "Copy as Markdown" puts a table on the clipboard. It pastes into a GitHub or GitLab issue, a README file or a wiki.
  • CSV: the file is UTF-8 with a byte order mark, comma-separated. An English-language Excel opens it in columns. LibreOffice Calc and Google Sheets read it too.
  • Print: "Print" outputs the title and the grid, without the rest of the page. The print dialog of the browser also saves it as a PDF.
  • Link: the address of the page carries the matrix, after the # sign. A browser does not send that part of the address to the server. "Copy the link" gives an address that reopens the same matrix.

The rules of a RACI matrix

  1. Every task has one A, and only one. That person decides and signs off the result.
  2. Every task has at least one R. Without an R, nobody does the work.
  3. The A can also be the R. The same person does the work and answers for it: the cell reads A/R.
  4. A task has few C. Each C is an opinion to collect before deciding. Someone whose answer can change the decision is a C, the others are I.
  5. An I signs off nothing. The I is told once the decision is made, and the task does not wait for an answer.
  6. The people named read the matrix. It is agreed with them at the start of the project, in a workshop or at the kick-off meeting.
  7. The matrix follows the project. It is corrected when someone joins, leaves or changes role, and when the scope changes.

The generator checks the first two rules after every change. It also reports a column with no letter at all: that role has no place in the table, or a row is missing.

Building a RACI matrix in six steps

  1. List the tasks or deliverables of the project, one per row. Write a verb and an object: "Write the specification", not "Specification".
  2. List the roles in columns. A role ("Tech lead") outlasts a name. A name spares the reader from asking who holds the role.
  3. Place the A of each row first.
  4. Place the R, then the C, then the I. A cell can stay empty.
  5. Read each row again: one A, at least one R. Read each column again: at least one letter.
  6. Send the link of the matrix to the people it names and correct it with them.

Three RACI matrix examples

A software project

Software project
TaskProduct managerTech leadDevelopersTester
Write the specificationA/RCCI
Develop the featureIARI
Review the codeAR
Test before releaseIICA/R
Release to productionIARC

On the "Review the code" row, the tech lead is A and the developers are R. The product manager and the tester have no letter there. On the "Test before release" row, the tester runs the tests and answers for them: the cell reads A/R.

A Scrum sprint

Scrum sprint
TaskProduct OwnerScrum MasterDevelopersStakeholders
Order the Product BacklogA/RCC
Sprint PlanningRRA/RC
Size the backlog itemsCA/R
Daily ScrumA/R
Sprint ReviewA/RRRC
Sprint RetrospectiveRA/RR

The 2020 Scrum Guide defines three accountabilities, not a RACI matrix: this table is one reading of it. Four rows come from the guide. The Product Owner is accountable for Product Backlog management, which includes its order. The Developers are accountable for the plan for the Sprint and are responsible for sizing the backlog items. The Daily Scrum is a 15-minute event for the Developers. The Scrum Master is accountable for the Scrum Team's effectiveness, which the retrospective inspects. The guide names no A for the Sprint Review: this table gives it to the Product Owner, who is accountable for the value of the product.

A product launch

Product launch
TaskProduct managerMarketingSalesSupport
Set the date and the scopeA/RCCI
Write the product page and the announcementARCI
Train the sales teamRCAI
Prepare the help pagesCIA/R
Publish the announcementIA/RII

On the "Train the sales team" row, the product manager gives the training (R) and sales answers for it (A). Support is I on four rows and A/R on the help pages.

RASCI, RACI-VS, DACI, RAPID: the variants

AcronymLettersWhat changes
RASCIResponsible, Accountable, Support, Consulted, InformedThe S helps the R do the task. Also written RASIC.
RACI-VSRACI, Verifier, SignatoryThe V checks the deliverable against its acceptance criteria, the S signs the handover.
DACIDriver, Approver, Contributors, InformedUsed to make a decision: the D drives it, a single A makes it.
RAPIDRecommend, Agree, Perform, Input, DecideA decision tool from the firm Bain & Company: the D decides, the P carries it out.

Common mistakes

  • Several A on one task. When they disagree, nobody knows who decides. Keep as A the person who signs off the result and make the others C.
  • No R. The task is signed off by someone and done by no one. Name an R before moving to the next row.
  • Everyone is a C. With six C, a decision waits for six opinions. Make I the people whose opinion does not change the decision.
  • Too many rows. Each extra row is one more row to read again and keep up to date. Group the tasks by deliverable: the generator stops at 30 tasks.
  • A matrix nobody updates. It describes the team of the day it was written. Read it again each time someone joins or leaves and each time the scope changes.

Where does the RACI matrix come from?

A RACI matrix is a responsibility assignment matrix, or RAM. The PMBOK Guide of the Project Management Institute describes that matrix and gives the RACI chart as an example. ITIL, the framework for IT service management, uses RACI as well.

Frequently asked questions

What does RACI stand for?

Responsible, Accountable, Consulted, Informed. The R does the task, the A answers for the result, the C gives an opinion before the decision, the I is told after it.

What is the difference between R and A?

The R does the work. The A answers for the result and signs it off. A task can have several R and has one A. When the same person does the work and answers for it, the cell reads A/R.

Can a task have more than one A?

No. A task has one A. With two, nobody knows who decides when they disagree. If two people sign off the work, keep as A the one who answers for the result and make the other a C.

RACI or RASCI?

RASCI adds one letter, S for Support: someone who helps the R do the task without answering for it. If nobody plays that part in your project, the four letters of RACI are enough.

How do I make a RACI matrix in Excel?

Fill in the matrix in the generator on this page, click "Download as CSV", then open the file in Excel. The file is UTF-8 with a byte order mark and comma-separated, which an English-language Excel opens in columns. In an empty sheet, put one task per row, one role per column and one letter per cell.